TF: 1.844.ESC(372).8877

Package Roof Mounted HVAC System
Package Roof Mounted HVAC System

HVAC

The selection of the best Heating / Ventilation / Air Conditioning (HVAC) Systems required for your Cleanroom, can vary with the requirements:

The HVAC system design is driven by the “Load” in the room, this is calculated by:

The amount of Heat Generated by the Process

The Ambient Conditions surrounding the Cleanroom

The amount of exhaust from the Cleanroom, and the Process

Sizing is then determined, and the control parameters are defined by the Temperature & Humidity Range, the larger the range, the easier the equipment selection process is.

To understand this relationship review our

Temperature Humidity Range Document

Systems can range from “Off the Shelf” standard Package systems, to Custom Manufactured Systems, that can Heat / Cool / Humidify & De Humidify, as well as Filter the Air.

We can help you understand the various systems available, and choose the best solution for your project.

Cleanroom Air Handling Room
Cleanroom Air Handling Room
Cleanroom Ductwork
Cleanroom Ductwork

Air Distribution

Air Distribution Systems are typically sheet metal ductwork, rectangular or Spiral.

Sizing is dependent on the total airflow, and the static pressure of the system.

Systems can be sized smaller for initial installation cost savings, however this will increase the fan horsepower requirements, and increase operating cost.

Insulation may be required and is installed on the exterior.

Pressure testing should be performed to insure that air is not leaking.

Duct joining systems are dependent on the size of the duct.

Duct Installation requires Clean Build Procedures, and an Inspection Report

We can help you understand the various systems available, and choose the best solution for your project.